Friday 1 November 2024

15/10/24

 from Mike

Jon went to end to check and it was diggable (left side still flooded), so Matilda filled all the buckets (except 2 with broken handles, although a third did go down and get filled - all taken to surface after). Digging was apparently fairly easy, then Ed passed them back to final haul, with Mike and Jon on either end, who also flattened out the conveyor belt and moved the middle sized rocks back to start of that haul. We then staged all buckets up to spoil heap and emptied them, leaving the tools and skip on shelf at start of final haul. It started to rain as we headed out just after 8.30, where we found Duncan and Fran (who had arrived late), but fortunately it didn't pour down until we left the waldegrave (everyone except Matilda)