Wednesday 14 October 2020

13/10/20

Estelle & James brought sand and cement and there was already some dust over there to make up a mix with, so we set to clearing where there had been a slump on the right of the steps. Tools recovered and removed to higher ground and James cleared all the mud away to reveal back to the previous cemented wall level. Dave made mix up while the spoil was removed and the rocks we'd taken out a couple of weeks back were brought back in for wall building! The big boulder at the top of the steps was undermined and then a wall built under it and cemented in place and continuation just below it until we ran out of mix for now. Will continue this over the next couple of weeks unless it happens to dry out enough to dig. The levels had dropped maybe 18" at most since Sunday, but still very much under water.

No comments:

Post a Comment

Note: only a member of this blog may post a comment.