Wednesday 11 September 2019

13/8/19


Estelle Sandford, James Begley, Jonathan Riley, Dave Walker, Chris Duberry
2hrs
James went in first, Chris turned up for the first time and brought 2 new tubs with him, so we’re now having to learn the 19x table. After James had filled 19, Chris took his turn and filled 19, then Estelle, then bonus 15 buckets and Dave got to dig too as we were motoring and it wasn’t yet pub ‘o’ clock! The ceiling seems to be coming down a bit on both left, right and in front. The passage on the right resembles the same red ledge as further up passage. There are some quite large boulders in the floor that could do with excavation and removal as it is possible we should be going down. Still a lot more clay to remove though to see what is going on more, but the chamber is getting quite a reasonable size now. Water levels hadn’t been affected by the recent heavy rains.