Wednesday 10 July 2024

9/7/24

Estelle Sandford, Mike Moxon, Stu Lindsay, Ed & Kat Ford, Jon Riley, Fran Campbell

1.5hrs

Stu continued putting in some additional handlines and drilling holes for bolts for that ahead of helping with the hauling. Estelle and Ed headed to the dig and Estelle digging down in the forward bit and Ed clearing the last of the flood spoil from the aven area. Going down is giving rocks in the floor after a layer of spoil, all seem to be fairly loose. All buckets filled and then taken out and some bag filling was done before retiring to the Waldy

Tuesday 9 July 2024

2/7/24

Report from Mike M

Mike Moxon, Ed Ford (MCG), Stu Lindsay, Fran Campbell, Duncan Butler, Jon Riley

2hours

Filled all 35ish buckets, Duncan clearing the front slump, then starting on digging forward, Mike loaded up about half of the aven slump, so it's now below the level of surrounding rocks. Ed Ford (MCG) and Fran started moving the tubs back whilst Jon brought in the two skip runs, after reattaching haul lines, then all 5 of us dragged everything back to the spoil heap, where we filled the low point in corner - buckets emptying easily. Whilst Stu did his with adding safety lines/drilling.


18/6/24

Report from Stu/Mike

18/6/24

James Begley, Mike Moxon, Jon Riley, Stu Lindsay, Fran Campbell

Some preparation work to aim to dig soon now the end has drained. Stu drilled a hole for a hanger for a safety line for the ladder, but the drill snapped off, so wasn’t able to complete the work. The rope supplied by Blitz is now in 2 pieces with one having 2/3rds of the necessary knots in, which Stu has taken home to complete.

Mike took a look at the right hand passage, looks much the same as previously but with extra slime from the floods, but a couple of rocks in the roof at the start have come out. He then dug a couple of rocks out from the collapse at the main end and there is about a dozen tubs worth of slump there and another half dozen below aven. Poured some water into end slot and it disappeared left out of view and gurgled away (probably more ahead direction), Finally removed both skips to daylight and filled a couple of buckets with mud from around the steps.